Installing the Failover Hardware Components
24
Failover Cluster Connections, Dual-Connected Configuration
Make the following cable connections to add a failover cluster to an Avid ISIS environment as a
dual-connected configuration:
First cluster node (AS3000):
- Top-right network interface connector (2) to the ISIS left subnet (VLAN 10 public
network)
- Bottom-right network interface connector (4) to the ISIS right subnet (VLAN 20 public
network)
- Bottom-left network interface connector (3) to the bottom-left network interface
connector on the second cluster node (private network for heartbeat)
- Fibre Channel connector on the ATTO Celerity FC-81EN card to Fibre Channel
connector Port 1 (top left) on the Infortrend RAID array or the HP MSA RAID array.
Second cluster node (AS3000):
- Top-right network interface connector (2) to the ISIS left subnet (VLAN 10 public
network)
- Bottom-right network interface connector (4) to the ISIS right subnet (VLAN 20 public
network)
- Bottom-left network interface connector (3) to the bottom-left network interface
connector on the first cluster node (private network for heartbeat)
- Fibre Channel connector on the ATTO Celerity FC-81EN card to Fibre Channel
connector Port 2 (bottom, second from left) on the Infortrend RAID array or the HP
MSA RAID array.
The following illustrations show these connections.